I need more construction workers
up vote
1
down vote
favorite
40 man working on a construction job had completed 1/3 of the jobs in the previous 15 days. The job was behind schedule, and needed to be completed 12 days from now. Additional workers needed to be hired an order to accomplish that. How many additional workers needed to be hired?
algebra-precalculus
add a comment |
up vote
1
down vote
favorite
40 man working on a construction job had completed 1/3 of the jobs in the previous 15 days. The job was behind schedule, and needed to be completed 12 days from now. Additional workers needed to be hired an order to accomplish that. How many additional workers needed to be hired?
algebra-precalculus
add a comment |
up vote
1
down vote
favorite
up vote
1
down vote
favorite
40 man working on a construction job had completed 1/3 of the jobs in the previous 15 days. The job was behind schedule, and needed to be completed 12 days from now. Additional workers needed to be hired an order to accomplish that. How many additional workers needed to be hired?
algebra-precalculus
40 man working on a construction job had completed 1/3 of the jobs in the previous 15 days. The job was behind schedule, and needed to be completed 12 days from now. Additional workers needed to be hired an order to accomplish that. How many additional workers needed to be hired?
algebra-precalculus
algebra-precalculus
edited Nov 13 at 0:41
Henning Makholm
235k16299534
235k16299534
asked Nov 13 at 0:09
user53536
51
51
add a comment |
add a comment |
2 Answers
2
active
oldest
votes
up vote
3
down vote
Your workers have contributed $15cdot 40 = 600$ man-days to the project.
This is $frac 13$ the required amount. The project requires $1800$ man*days.
You still need to apply $1200$ man*days
$frac {1200 text {man*days}}{12 text {days}} = 100$ men
or 60 additional men.
1
Simple and effective.
– Henning Makholm
Nov 13 at 0:46
add a comment |
up vote
2
down vote
I think the answer is ( roll mouse over to reveal answer and working )
60 more workers
because
40 did 1/3 of the work in 15 days. so 2/3 of the work remains, which would take 80 workers 15 days, but it needs to be 12 days so we multiply by 5/4 and need total of 100 workers, which is 60 more. NB 5/4 is 15/12 - the 'speed up ratio' required to go from 15 days to 12 days.
Now....
This answer relies on everything being 'linear'. So the assumption that 80 workers get twice as much done per day as 40 workers is an assumption of linearity. In the real world, of course, problems are often non-linear. But I like this problem as it has several steps and twists along the way. Such as 1/3 of the work is already done and the way the question asks for the number of additional workers required.
add a comment |
2 Answers
2
active
oldest
votes
2 Answers
2
active
oldest
votes
active
oldest
votes
active
oldest
votes
up vote
3
down vote
Your workers have contributed $15cdot 40 = 600$ man-days to the project.
This is $frac 13$ the required amount. The project requires $1800$ man*days.
You still need to apply $1200$ man*days
$frac {1200 text {man*days}}{12 text {days}} = 100$ men
or 60 additional men.
1
Simple and effective.
– Henning Makholm
Nov 13 at 0:46
add a comment |
up vote
3
down vote
Your workers have contributed $15cdot 40 = 600$ man-days to the project.
This is $frac 13$ the required amount. The project requires $1800$ man*days.
You still need to apply $1200$ man*days
$frac {1200 text {man*days}}{12 text {days}} = 100$ men
or 60 additional men.
1
Simple and effective.
– Henning Makholm
Nov 13 at 0:46
add a comment |
up vote
3
down vote
up vote
3
down vote
Your workers have contributed $15cdot 40 = 600$ man-days to the project.
This is $frac 13$ the required amount. The project requires $1800$ man*days.
You still need to apply $1200$ man*days
$frac {1200 text {man*days}}{12 text {days}} = 100$ men
or 60 additional men.
Your workers have contributed $15cdot 40 = 600$ man-days to the project.
This is $frac 13$ the required amount. The project requires $1800$ man*days.
You still need to apply $1200$ man*days
$frac {1200 text {man*days}}{12 text {days}} = 100$ men
or 60 additional men.
edited Nov 13 at 0:38
answered Nov 13 at 0:22
Doug M
42.6k31752
42.6k31752
1
Simple and effective.
– Henning Makholm
Nov 13 at 0:46
add a comment |
1
Simple and effective.
– Henning Makholm
Nov 13 at 0:46
1
1
Simple and effective.
– Henning Makholm
Nov 13 at 0:46
Simple and effective.
– Henning Makholm
Nov 13 at 0:46
add a comment |
up vote
2
down vote
I think the answer is ( roll mouse over to reveal answer and working )
60 more workers
because
40 did 1/3 of the work in 15 days. so 2/3 of the work remains, which would take 80 workers 15 days, but it needs to be 12 days so we multiply by 5/4 and need total of 100 workers, which is 60 more. NB 5/4 is 15/12 - the 'speed up ratio' required to go from 15 days to 12 days.
Now....
This answer relies on everything being 'linear'. So the assumption that 80 workers get twice as much done per day as 40 workers is an assumption of linearity. In the real world, of course, problems are often non-linear. But I like this problem as it has several steps and twists along the way. Such as 1/3 of the work is already done and the way the question asks for the number of additional workers required.
add a comment |
up vote
2
down vote
I think the answer is ( roll mouse over to reveal answer and working )
60 more workers
because
40 did 1/3 of the work in 15 days. so 2/3 of the work remains, which would take 80 workers 15 days, but it needs to be 12 days so we multiply by 5/4 and need total of 100 workers, which is 60 more. NB 5/4 is 15/12 - the 'speed up ratio' required to go from 15 days to 12 days.
Now....
This answer relies on everything being 'linear'. So the assumption that 80 workers get twice as much done per day as 40 workers is an assumption of linearity. In the real world, of course, problems are often non-linear. But I like this problem as it has several steps and twists along the way. Such as 1/3 of the work is already done and the way the question asks for the number of additional workers required.
add a comment |
up vote
2
down vote
up vote
2
down vote
I think the answer is ( roll mouse over to reveal answer and working )
60 more workers
because
40 did 1/3 of the work in 15 days. so 2/3 of the work remains, which would take 80 workers 15 days, but it needs to be 12 days so we multiply by 5/4 and need total of 100 workers, which is 60 more. NB 5/4 is 15/12 - the 'speed up ratio' required to go from 15 days to 12 days.
Now....
This answer relies on everything being 'linear'. So the assumption that 80 workers get twice as much done per day as 40 workers is an assumption of linearity. In the real world, of course, problems are often non-linear. But I like this problem as it has several steps and twists along the way. Such as 1/3 of the work is already done and the way the question asks for the number of additional workers required.
I think the answer is ( roll mouse over to reveal answer and working )
60 more workers
because
40 did 1/3 of the work in 15 days. so 2/3 of the work remains, which would take 80 workers 15 days, but it needs to be 12 days so we multiply by 5/4 and need total of 100 workers, which is 60 more. NB 5/4 is 15/12 - the 'speed up ratio' required to go from 15 days to 12 days.
Now....
This answer relies on everything being 'linear'. So the assumption that 80 workers get twice as much done per day as 40 workers is an assumption of linearity. In the real world, of course, problems are often non-linear. But I like this problem as it has several steps and twists along the way. Such as 1/3 of the work is already done and the way the question asks for the number of additional workers required.
edited Nov 13 at 0:34
answered Nov 13 at 0:16
tom
1429
1429
add a comment |
add a comment |
Sign up or log in
StackExchange.ready(function () {
StackExchange.helpers.onClickDraftSave('#login-link');
});
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Required, but never shown
StackExchange.ready(
function () {
StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fmath.stackexchange.com%2fquestions%2f2996090%2fi-need-more-construction-workers%23new-answer', 'question_page');
}
);
Post as a guest
Required, but never shown
Sign up or log in
StackExchange.ready(function () {
StackExchange.helpers.onClickDraftSave('#login-link');
});
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Required, but never shown
Sign up or log in
StackExchange.ready(function () {
StackExchange.helpers.onClickDraftSave('#login-link');
});
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Required, but never shown
Sign up or log in
StackExchange.ready(function () {
StackExchange.helpers.onClickDraftSave('#login-link');
});
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown