I need more construction workers











up vote
1
down vote

favorite












40 man working on a construction job had completed 1/3 of the jobs in the previous 15 days. The job was behind schedule, and needed to be completed 12 days from now. Additional workers needed to be hired an order to accomplish that. How many additional workers needed to be hired?










share|cite|improve this question




























    up vote
    1
    down vote

    favorite












    40 man working on a construction job had completed 1/3 of the jobs in the previous 15 days. The job was behind schedule, and needed to be completed 12 days from now. Additional workers needed to be hired an order to accomplish that. How many additional workers needed to be hired?










    share|cite|improve this question


























      up vote
      1
      down vote

      favorite









      up vote
      1
      down vote

      favorite











      40 man working on a construction job had completed 1/3 of the jobs in the previous 15 days. The job was behind schedule, and needed to be completed 12 days from now. Additional workers needed to be hired an order to accomplish that. How many additional workers needed to be hired?










      share|cite|improve this question















      40 man working on a construction job had completed 1/3 of the jobs in the previous 15 days. The job was behind schedule, and needed to be completed 12 days from now. Additional workers needed to be hired an order to accomplish that. How many additional workers needed to be hired?







      algebra-precalculus






      share|cite|improve this question















      share|cite|improve this question













      share|cite|improve this question




      share|cite|improve this question








      edited Nov 13 at 0:41









      Henning Makholm

      235k16299534




      235k16299534










      asked Nov 13 at 0:09









      user53536

      51




      51






















          2 Answers
          2






          active

          oldest

          votes

















          up vote
          3
          down vote













          Your workers have contributed $15cdot 40 = 600$ man-days to the project.



          This is $frac 13$ the required amount. The project requires $1800$ man*days.



          You still need to apply $1200$ man*days



          $frac {1200 text {man*days}}{12 text {days}} = 100$ men



          or 60 additional men.






          share|cite|improve this answer



















          • 1




            Simple and effective.
            – Henning Makholm
            Nov 13 at 0:46


















          up vote
          2
          down vote













          I think the answer is ( roll mouse over to reveal answer and working )




          60 more workers




          because




          40 did 1/3 of the work in 15 days. so 2/3 of the work remains, which would take 80 workers 15 days, but it needs to be 12 days so we multiply by 5/4 and need total of 100 workers, which is 60 more. NB 5/4 is 15/12 - the 'speed up ratio' required to go from 15 days to 12 days.




          Now....




          This answer relies on everything being 'linear'. So the assumption that 80 workers get twice as much done per day as 40 workers is an assumption of linearity. In the real world, of course, problems are often non-linear. But I like this problem as it has several steps and twists along the way. Such as 1/3 of the work is already done and the way the question asks for the number of additional workers required.







          share|cite|improve this answer























            Your Answer





            StackExchange.ifUsing("editor", function () {
            return StackExchange.using("mathjaxEditing", function () {
            StackExchange.MarkdownEditor.creationCallbacks.add(function (editor, postfix) {
            StackExchange.mathjaxEditing.prepareWmdForMathJax(editor, postfix, [["$", "$"], ["\\(","\\)"]]);
            });
            });
            }, "mathjax-editing");

            StackExchange.ready(function() {
            var channelOptions = {
            tags: "".split(" "),
            id: "69"
            };
            initTagRenderer("".split(" "), "".split(" "), channelOptions);

            StackExchange.using("externalEditor", function() {
            // Have to fire editor after snippets, if snippets enabled
            if (StackExchange.settings.snippets.snippetsEnabled) {
            StackExchange.using("snippets", function() {
            createEditor();
            });
            }
            else {
            createEditor();
            }
            });

            function createEditor() {
            StackExchange.prepareEditor({
            heartbeatType: 'answer',
            convertImagesToLinks: true,
            noModals: true,
            showLowRepImageUploadWarning: true,
            reputationToPostImages: 10,
            bindNavPrevention: true,
            postfix: "",
            imageUploader: {
            brandingHtml: "Powered by u003ca class="icon-imgur-white" href="https://imgur.com/"u003eu003c/au003e",
            contentPolicyHtml: "User contributions licensed under u003ca href="https://creativecommons.org/licenses/by-sa/3.0/"u003ecc by-sa 3.0 with attribution requiredu003c/au003e u003ca href="https://stackoverflow.com/legal/content-policy"u003e(content policy)u003c/au003e",
            allowUrls: true
            },
            noCode: true, onDemand: true,
            discardSelector: ".discard-answer"
            ,immediatelyShowMarkdownHelp:true
            });


            }
            });














             

            draft saved


            draft discarded


















            StackExchange.ready(
            function () {
            StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fmath.stackexchange.com%2fquestions%2f2996090%2fi-need-more-construction-workers%23new-answer', 'question_page');
            }
            );

            Post as a guest















            Required, but never shown

























            2 Answers
            2






            active

            oldest

            votes








            2 Answers
            2






            active

            oldest

            votes









            active

            oldest

            votes






            active

            oldest

            votes








            up vote
            3
            down vote













            Your workers have contributed $15cdot 40 = 600$ man-days to the project.



            This is $frac 13$ the required amount. The project requires $1800$ man*days.



            You still need to apply $1200$ man*days



            $frac {1200 text {man*days}}{12 text {days}} = 100$ men



            or 60 additional men.






            share|cite|improve this answer



















            • 1




              Simple and effective.
              – Henning Makholm
              Nov 13 at 0:46















            up vote
            3
            down vote













            Your workers have contributed $15cdot 40 = 600$ man-days to the project.



            This is $frac 13$ the required amount. The project requires $1800$ man*days.



            You still need to apply $1200$ man*days



            $frac {1200 text {man*days}}{12 text {days}} = 100$ men



            or 60 additional men.






            share|cite|improve this answer



















            • 1




              Simple and effective.
              – Henning Makholm
              Nov 13 at 0:46













            up vote
            3
            down vote










            up vote
            3
            down vote









            Your workers have contributed $15cdot 40 = 600$ man-days to the project.



            This is $frac 13$ the required amount. The project requires $1800$ man*days.



            You still need to apply $1200$ man*days



            $frac {1200 text {man*days}}{12 text {days}} = 100$ men



            or 60 additional men.






            share|cite|improve this answer














            Your workers have contributed $15cdot 40 = 600$ man-days to the project.



            This is $frac 13$ the required amount. The project requires $1800$ man*days.



            You still need to apply $1200$ man*days



            $frac {1200 text {man*days}}{12 text {days}} = 100$ men



            or 60 additional men.







            share|cite|improve this answer














            share|cite|improve this answer



            share|cite|improve this answer








            edited Nov 13 at 0:38

























            answered Nov 13 at 0:22









            Doug M

            42.6k31752




            42.6k31752








            • 1




              Simple and effective.
              – Henning Makholm
              Nov 13 at 0:46














            • 1




              Simple and effective.
              – Henning Makholm
              Nov 13 at 0:46








            1




            1




            Simple and effective.
            – Henning Makholm
            Nov 13 at 0:46




            Simple and effective.
            – Henning Makholm
            Nov 13 at 0:46










            up vote
            2
            down vote













            I think the answer is ( roll mouse over to reveal answer and working )




            60 more workers




            because




            40 did 1/3 of the work in 15 days. so 2/3 of the work remains, which would take 80 workers 15 days, but it needs to be 12 days so we multiply by 5/4 and need total of 100 workers, which is 60 more. NB 5/4 is 15/12 - the 'speed up ratio' required to go from 15 days to 12 days.




            Now....




            This answer relies on everything being 'linear'. So the assumption that 80 workers get twice as much done per day as 40 workers is an assumption of linearity. In the real world, of course, problems are often non-linear. But I like this problem as it has several steps and twists along the way. Such as 1/3 of the work is already done and the way the question asks for the number of additional workers required.







            share|cite|improve this answer



























              up vote
              2
              down vote













              I think the answer is ( roll mouse over to reveal answer and working )




              60 more workers




              because




              40 did 1/3 of the work in 15 days. so 2/3 of the work remains, which would take 80 workers 15 days, but it needs to be 12 days so we multiply by 5/4 and need total of 100 workers, which is 60 more. NB 5/4 is 15/12 - the 'speed up ratio' required to go from 15 days to 12 days.




              Now....




              This answer relies on everything being 'linear'. So the assumption that 80 workers get twice as much done per day as 40 workers is an assumption of linearity. In the real world, of course, problems are often non-linear. But I like this problem as it has several steps and twists along the way. Such as 1/3 of the work is already done and the way the question asks for the number of additional workers required.







              share|cite|improve this answer

























                up vote
                2
                down vote










                up vote
                2
                down vote









                I think the answer is ( roll mouse over to reveal answer and working )




                60 more workers




                because




                40 did 1/3 of the work in 15 days. so 2/3 of the work remains, which would take 80 workers 15 days, but it needs to be 12 days so we multiply by 5/4 and need total of 100 workers, which is 60 more. NB 5/4 is 15/12 - the 'speed up ratio' required to go from 15 days to 12 days.




                Now....




                This answer relies on everything being 'linear'. So the assumption that 80 workers get twice as much done per day as 40 workers is an assumption of linearity. In the real world, of course, problems are often non-linear. But I like this problem as it has several steps and twists along the way. Such as 1/3 of the work is already done and the way the question asks for the number of additional workers required.







                share|cite|improve this answer














                I think the answer is ( roll mouse over to reveal answer and working )




                60 more workers




                because




                40 did 1/3 of the work in 15 days. so 2/3 of the work remains, which would take 80 workers 15 days, but it needs to be 12 days so we multiply by 5/4 and need total of 100 workers, which is 60 more. NB 5/4 is 15/12 - the 'speed up ratio' required to go from 15 days to 12 days.




                Now....




                This answer relies on everything being 'linear'. So the assumption that 80 workers get twice as much done per day as 40 workers is an assumption of linearity. In the real world, of course, problems are often non-linear. But I like this problem as it has several steps and twists along the way. Such as 1/3 of the work is already done and the way the question asks for the number of additional workers required.








                share|cite|improve this answer














                share|cite|improve this answer



                share|cite|improve this answer








                edited Nov 13 at 0:34

























                answered Nov 13 at 0:16









                tom

                1429




                1429






























                     

                    draft saved


                    draft discarded



















































                     


                    draft saved


                    draft discarded














                    StackExchange.ready(
                    function () {
                    StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fmath.stackexchange.com%2fquestions%2f2996090%2fi-need-more-construction-workers%23new-answer', 'question_page');
                    }
                    );

                    Post as a guest















                    Required, but never shown





















































                    Required, but never shown














                    Required, but never shown












                    Required, but never shown







                    Required, but never shown

































                    Required, but never shown














                    Required, but never shown












                    Required, but never shown







                    Required, but never shown







                    Popular posts from this blog

                    How to send String Array data to Server using php in android

                    Title Spacing in Bjornstrup Chapter, Removing Chapter Number From Contents

                    Is anime1.com a legal site for watching anime?