Normalizing Time Periods to Compare Them











up vote
1
down vote

favorite
2












I am working on a project where I am trying to compare the number of projects completed in various, discrete time periods. The time periods are categorical (if that matters).



The thing is that each time period has a different number of days and people working on the projects that were completed in that time period.



In order to compare the time periods, I took the number of people working in each time period and divided that by the largest number of people in any time period to get a people normalizer. I did the same thing for the number of days in each period, dividing the number of days in each period by the number of days in the period with the most days. Thus, these normalizers are on a 0 to 1 scale with the period with the greatest number of people and days having a score of 1.



Then I multiplied the day and people normalizers for each period to get an overall normalizer. I then divided the non-normalized number of projects in each time period by the combined day and person normalizers to get the adjusted, normalized number of projects.



Example



Period 1: 65 days. 8 people, 5 projects completed.



Period 2: 85 days, 9 people. 6 projects completed.



Period 3: 90 days, 10 people, 4 projects completed.



I want to normalize these three periods so that I'm comparing how productive each period was given the number of people and days.



Is this a legitimate way of normalizing these time periods so they can be compared to each other?










share|cite|improve this question
























  • I suggest you give a small example. Also, when you say "compare", what do you want to compare exactly? What units?
    – NoChance
    Nov 17 at 0:04










  • Thanks for your reply. Here is an example: Period 1: 65 days. 8 people, 5 projects completed. Period 2: 85 days, 9 people. 6 projects completed. Period 3: 90 days, 10 people, 4 projects completed. I was to normalize these three periods so that I'm comparing how productive each period was given the number of people and days.
    – rfhickey
    Nov 17 at 0:05












  • The question is interesting, I suggest you post it on: pm.stackexchange.com
    – NoChance
    Nov 17 at 0:30










  • Are you looking for the productivity of people? Just divide time by number of projects and number of people assuming that the projects have same difficulty level.
    – Moti
    Nov 17 at 6:22










  • @NoChance Thanks. I may do that!
    – rfhickey
    Nov 17 at 15:40















up vote
1
down vote

favorite
2












I am working on a project where I am trying to compare the number of projects completed in various, discrete time periods. The time periods are categorical (if that matters).



The thing is that each time period has a different number of days and people working on the projects that were completed in that time period.



In order to compare the time periods, I took the number of people working in each time period and divided that by the largest number of people in any time period to get a people normalizer. I did the same thing for the number of days in each period, dividing the number of days in each period by the number of days in the period with the most days. Thus, these normalizers are on a 0 to 1 scale with the period with the greatest number of people and days having a score of 1.



Then I multiplied the day and people normalizers for each period to get an overall normalizer. I then divided the non-normalized number of projects in each time period by the combined day and person normalizers to get the adjusted, normalized number of projects.



Example



Period 1: 65 days. 8 people, 5 projects completed.



Period 2: 85 days, 9 people. 6 projects completed.



Period 3: 90 days, 10 people, 4 projects completed.



I want to normalize these three periods so that I'm comparing how productive each period was given the number of people and days.



Is this a legitimate way of normalizing these time periods so they can be compared to each other?










share|cite|improve this question
























  • I suggest you give a small example. Also, when you say "compare", what do you want to compare exactly? What units?
    – NoChance
    Nov 17 at 0:04










  • Thanks for your reply. Here is an example: Period 1: 65 days. 8 people, 5 projects completed. Period 2: 85 days, 9 people. 6 projects completed. Period 3: 90 days, 10 people, 4 projects completed. I was to normalize these three periods so that I'm comparing how productive each period was given the number of people and days.
    – rfhickey
    Nov 17 at 0:05












  • The question is interesting, I suggest you post it on: pm.stackexchange.com
    – NoChance
    Nov 17 at 0:30










  • Are you looking for the productivity of people? Just divide time by number of projects and number of people assuming that the projects have same difficulty level.
    – Moti
    Nov 17 at 6:22










  • @NoChance Thanks. I may do that!
    – rfhickey
    Nov 17 at 15:40













up vote
1
down vote

favorite
2









up vote
1
down vote

favorite
2






2





I am working on a project where I am trying to compare the number of projects completed in various, discrete time periods. The time periods are categorical (if that matters).



The thing is that each time period has a different number of days and people working on the projects that were completed in that time period.



In order to compare the time periods, I took the number of people working in each time period and divided that by the largest number of people in any time period to get a people normalizer. I did the same thing for the number of days in each period, dividing the number of days in each period by the number of days in the period with the most days. Thus, these normalizers are on a 0 to 1 scale with the period with the greatest number of people and days having a score of 1.



Then I multiplied the day and people normalizers for each period to get an overall normalizer. I then divided the non-normalized number of projects in each time period by the combined day and person normalizers to get the adjusted, normalized number of projects.



Example



Period 1: 65 days. 8 people, 5 projects completed.



Period 2: 85 days, 9 people. 6 projects completed.



Period 3: 90 days, 10 people, 4 projects completed.



I want to normalize these three periods so that I'm comparing how productive each period was given the number of people and days.



Is this a legitimate way of normalizing these time periods so they can be compared to each other?










share|cite|improve this question















I am working on a project where I am trying to compare the number of projects completed in various, discrete time periods. The time periods are categorical (if that matters).



The thing is that each time period has a different number of days and people working on the projects that were completed in that time period.



In order to compare the time periods, I took the number of people working in each time period and divided that by the largest number of people in any time period to get a people normalizer. I did the same thing for the number of days in each period, dividing the number of days in each period by the number of days in the period with the most days. Thus, these normalizers are on a 0 to 1 scale with the period with the greatest number of people and days having a score of 1.



Then I multiplied the day and people normalizers for each period to get an overall normalizer. I then divided the non-normalized number of projects in each time period by the combined day and person normalizers to get the adjusted, normalized number of projects.



Example



Period 1: 65 days. 8 people, 5 projects completed.



Period 2: 85 days, 9 people. 6 projects completed.



Period 3: 90 days, 10 people, 4 projects completed.



I want to normalize these three periods so that I'm comparing how productive each period was given the number of people and days.



Is this a legitimate way of normalizing these time periods so they can be compared to each other?







algebra-precalculus






share|cite|improve this question















share|cite|improve this question













share|cite|improve this question




share|cite|improve this question








edited Nov 17 at 0:13

























asked Nov 16 at 23:56









rfhickey

64




64












  • I suggest you give a small example. Also, when you say "compare", what do you want to compare exactly? What units?
    – NoChance
    Nov 17 at 0:04










  • Thanks for your reply. Here is an example: Period 1: 65 days. 8 people, 5 projects completed. Period 2: 85 days, 9 people. 6 projects completed. Period 3: 90 days, 10 people, 4 projects completed. I was to normalize these three periods so that I'm comparing how productive each period was given the number of people and days.
    – rfhickey
    Nov 17 at 0:05












  • The question is interesting, I suggest you post it on: pm.stackexchange.com
    – NoChance
    Nov 17 at 0:30










  • Are you looking for the productivity of people? Just divide time by number of projects and number of people assuming that the projects have same difficulty level.
    – Moti
    Nov 17 at 6:22










  • @NoChance Thanks. I may do that!
    – rfhickey
    Nov 17 at 15:40


















  • I suggest you give a small example. Also, when you say "compare", what do you want to compare exactly? What units?
    – NoChance
    Nov 17 at 0:04










  • Thanks for your reply. Here is an example: Period 1: 65 days. 8 people, 5 projects completed. Period 2: 85 days, 9 people. 6 projects completed. Period 3: 90 days, 10 people, 4 projects completed. I was to normalize these three periods so that I'm comparing how productive each period was given the number of people and days.
    – rfhickey
    Nov 17 at 0:05












  • The question is interesting, I suggest you post it on: pm.stackexchange.com
    – NoChance
    Nov 17 at 0:30










  • Are you looking for the productivity of people? Just divide time by number of projects and number of people assuming that the projects have same difficulty level.
    – Moti
    Nov 17 at 6:22










  • @NoChance Thanks. I may do that!
    – rfhickey
    Nov 17 at 15:40
















I suggest you give a small example. Also, when you say "compare", what do you want to compare exactly? What units?
– NoChance
Nov 17 at 0:04




I suggest you give a small example. Also, when you say "compare", what do you want to compare exactly? What units?
– NoChance
Nov 17 at 0:04












Thanks for your reply. Here is an example: Period 1: 65 days. 8 people, 5 projects completed. Period 2: 85 days, 9 people. 6 projects completed. Period 3: 90 days, 10 people, 4 projects completed. I was to normalize these three periods so that I'm comparing how productive each period was given the number of people and days.
– rfhickey
Nov 17 at 0:05






Thanks for your reply. Here is an example: Period 1: 65 days. 8 people, 5 projects completed. Period 2: 85 days, 9 people. 6 projects completed. Period 3: 90 days, 10 people, 4 projects completed. I was to normalize these three periods so that I'm comparing how productive each period was given the number of people and days.
– rfhickey
Nov 17 at 0:05














The question is interesting, I suggest you post it on: pm.stackexchange.com
– NoChance
Nov 17 at 0:30




The question is interesting, I suggest you post it on: pm.stackexchange.com
– NoChance
Nov 17 at 0:30












Are you looking for the productivity of people? Just divide time by number of projects and number of people assuming that the projects have same difficulty level.
– Moti
Nov 17 at 6:22




Are you looking for the productivity of people? Just divide time by number of projects and number of people assuming that the projects have same difficulty level.
– Moti
Nov 17 at 6:22












@NoChance Thanks. I may do that!
– rfhickey
Nov 17 at 15:40




@NoChance Thanks. I may do that!
– rfhickey
Nov 17 at 15:40










1 Answer
1






active

oldest

votes

















up vote
0
down vote













Project 1. 13 × 8 people days per project.

That is how to rank them, by people days per project.

That is simple and should be sufficient for comparesions.



If you need some complicated ranking number, then

divide the people days per project by some arbitrary

number like m, the maximum people days per project.



If you want higher rating to be better in a limited

economic sense, then use 1 - m, a number you

may want to multiply by 100 for a % like rating.






share|cite|improve this answer





















  • This is a really interesting solution. Basically, it seems to me that by performing this calculation that you will get a percentage of how much faster the average project was completed in each period compared to the period where projects were completed the slowest on average. Is that correct? So in the examples I provided above, the largest number of people days used for the average project (225) was period 3 and the lowest was period 1 (104). 104/225 =.46 and 1 - .46 = .54. .54 times 100 = 54. So projects were completed on average 54% faster in period 1 than in period 3. That what you meant?
    – rfhickey
    Nov 17 at 16:13











Your Answer





StackExchange.ifUsing("editor", function () {
return StackExchange.using("mathjaxEditing", function () {
StackExchange.MarkdownEditor.creationCallbacks.add(function (editor, postfix) {
StackExchange.mathjaxEditing.prepareWmdForMathJax(editor, postfix, [["$", "$"], ["\\(","\\)"]]);
});
});
}, "mathjax-editing");

StackExchange.ready(function() {
var channelOptions = {
tags: "".split(" "),
id: "69"
};
initTagRenderer("".split(" "), "".split(" "), channelOptions);

StackExchange.using("externalEditor", function() {
// Have to fire editor after snippets, if snippets enabled
if (StackExchange.settings.snippets.snippetsEnabled) {
StackExchange.using("snippets", function() {
createEditor();
});
}
else {
createEditor();
}
});

function createEditor() {
StackExchange.prepareEditor({
heartbeatType: 'answer',
convertImagesToLinks: true,
noModals: true,
showLowRepImageUploadWarning: true,
reputationToPostImages: 10,
bindNavPrevention: true,
postfix: "",
imageUploader: {
brandingHtml: "Powered by u003ca class="icon-imgur-white" href="https://imgur.com/"u003eu003c/au003e",
contentPolicyHtml: "User contributions licensed under u003ca href="https://creativecommons.org/licenses/by-sa/3.0/"u003ecc by-sa 3.0 with attribution requiredu003c/au003e u003ca href="https://stackoverflow.com/legal/content-policy"u003e(content policy)u003c/au003e",
allowUrls: true
},
noCode: true, onDemand: true,
discardSelector: ".discard-answer"
,immediatelyShowMarkdownHelp:true
});


}
});














draft saved

draft discarded


















StackExchange.ready(
function () {
StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fmath.stackexchange.com%2fquestions%2f3001797%2fnormalizing-time-periods-to-compare-them%23new-answer', 'question_page');
}
);

Post as a guest















Required, but never shown

























1 Answer
1






active

oldest

votes








1 Answer
1






active

oldest

votes









active

oldest

votes






active

oldest

votes








up vote
0
down vote













Project 1. 13 × 8 people days per project.

That is how to rank them, by people days per project.

That is simple and should be sufficient for comparesions.



If you need some complicated ranking number, then

divide the people days per project by some arbitrary

number like m, the maximum people days per project.



If you want higher rating to be better in a limited

economic sense, then use 1 - m, a number you

may want to multiply by 100 for a % like rating.






share|cite|improve this answer





















  • This is a really interesting solution. Basically, it seems to me that by performing this calculation that you will get a percentage of how much faster the average project was completed in each period compared to the period where projects were completed the slowest on average. Is that correct? So in the examples I provided above, the largest number of people days used for the average project (225) was period 3 and the lowest was period 1 (104). 104/225 =.46 and 1 - .46 = .54. .54 times 100 = 54. So projects were completed on average 54% faster in period 1 than in period 3. That what you meant?
    – rfhickey
    Nov 17 at 16:13















up vote
0
down vote













Project 1. 13 × 8 people days per project.

That is how to rank them, by people days per project.

That is simple and should be sufficient for comparesions.



If you need some complicated ranking number, then

divide the people days per project by some arbitrary

number like m, the maximum people days per project.



If you want higher rating to be better in a limited

economic sense, then use 1 - m, a number you

may want to multiply by 100 for a % like rating.






share|cite|improve this answer





















  • This is a really interesting solution. Basically, it seems to me that by performing this calculation that you will get a percentage of how much faster the average project was completed in each period compared to the period where projects were completed the slowest on average. Is that correct? So in the examples I provided above, the largest number of people days used for the average project (225) was period 3 and the lowest was period 1 (104). 104/225 =.46 and 1 - .46 = .54. .54 times 100 = 54. So projects were completed on average 54% faster in period 1 than in period 3. That what you meant?
    – rfhickey
    Nov 17 at 16:13













up vote
0
down vote










up vote
0
down vote









Project 1. 13 × 8 people days per project.

That is how to rank them, by people days per project.

That is simple and should be sufficient for comparesions.



If you need some complicated ranking number, then

divide the people days per project by some arbitrary

number like m, the maximum people days per project.



If you want higher rating to be better in a limited

economic sense, then use 1 - m, a number you

may want to multiply by 100 for a % like rating.






share|cite|improve this answer












Project 1. 13 × 8 people days per project.

That is how to rank them, by people days per project.

That is simple and should be sufficient for comparesions.



If you need some complicated ranking number, then

divide the people days per project by some arbitrary

number like m, the maximum people days per project.



If you want higher rating to be better in a limited

economic sense, then use 1 - m, a number you

may want to multiply by 100 for a % like rating.







share|cite|improve this answer












share|cite|improve this answer



share|cite|improve this answer










answered Nov 17 at 8:34









William Elliot

6,9052518




6,9052518












  • This is a really interesting solution. Basically, it seems to me that by performing this calculation that you will get a percentage of how much faster the average project was completed in each period compared to the period where projects were completed the slowest on average. Is that correct? So in the examples I provided above, the largest number of people days used for the average project (225) was period 3 and the lowest was period 1 (104). 104/225 =.46 and 1 - .46 = .54. .54 times 100 = 54. So projects were completed on average 54% faster in period 1 than in period 3. That what you meant?
    – rfhickey
    Nov 17 at 16:13


















  • This is a really interesting solution. Basically, it seems to me that by performing this calculation that you will get a percentage of how much faster the average project was completed in each period compared to the period where projects were completed the slowest on average. Is that correct? So in the examples I provided above, the largest number of people days used for the average project (225) was period 3 and the lowest was period 1 (104). 104/225 =.46 and 1 - .46 = .54. .54 times 100 = 54. So projects were completed on average 54% faster in period 1 than in period 3. That what you meant?
    – rfhickey
    Nov 17 at 16:13
















This is a really interesting solution. Basically, it seems to me that by performing this calculation that you will get a percentage of how much faster the average project was completed in each period compared to the period where projects were completed the slowest on average. Is that correct? So in the examples I provided above, the largest number of people days used for the average project (225) was period 3 and the lowest was period 1 (104). 104/225 =.46 and 1 - .46 = .54. .54 times 100 = 54. So projects were completed on average 54% faster in period 1 than in period 3. That what you meant?
– rfhickey
Nov 17 at 16:13




This is a really interesting solution. Basically, it seems to me that by performing this calculation that you will get a percentage of how much faster the average project was completed in each period compared to the period where projects were completed the slowest on average. Is that correct? So in the examples I provided above, the largest number of people days used for the average project (225) was period 3 and the lowest was period 1 (104). 104/225 =.46 and 1 - .46 = .54. .54 times 100 = 54. So projects were completed on average 54% faster in period 1 than in period 3. That what you meant?
– rfhickey
Nov 17 at 16:13


















draft saved

draft discarded




















































Thanks for contributing an answer to Mathematics Stack Exchange!


  • Please be sure to answer the question. Provide details and share your research!

But avoid



  • Asking for help, clarification, or responding to other answers.

  • Making statements based on opinion; back them up with references or personal experience.


Use MathJax to format equations. MathJax reference.


To learn more, see our tips on writing great answers.





Some of your past answers have not been well-received, and you're in danger of being blocked from answering.


Please pay close attention to the following guidance:


  • Please be sure to answer the question. Provide details and share your research!

But avoid



  • Asking for help, clarification, or responding to other answers.

  • Making statements based on opinion; back them up with references or personal experience.


To learn more, see our tips on writing great answers.




draft saved


draft discarded














StackExchange.ready(
function () {
StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fmath.stackexchange.com%2fquestions%2f3001797%2fnormalizing-time-periods-to-compare-them%23new-answer', 'question_page');
}
);

Post as a guest















Required, but never shown





















































Required, but never shown














Required, but never shown












Required, but never shown







Required, but never shown

































Required, but never shown














Required, but never shown












Required, but never shown







Required, but never shown







Popular posts from this blog

How to change which sound is reproduced for terminal bell?

Can I use Tabulator js library in my java Spring + Thymeleaf project?

Title Spacing in Bjornstrup Chapter, Removing Chapter Number From Contents